October 2019

Notify public of CPP application

We are required to publicly notify our intention to seek a CPP 40 days before
making a submission to the Commerce Commission.
November 2019

Draft CPP Proposal published in Your Network, Your Say consultation document

12 June 2020

Submission of CPP Application with revised CPP proposal to regulator

We’ll apply to the Commerce Commission for a customised price-quality path by
submitting our final proposal for our future investment plan. We’ll explain
how feedback from customers shaped our views.
30 July 2020

Commerce Commission process and issues paper due

The Commerce Commission will decide within 40 working days of receiving a proposal
whether it is complete. If the proposal is accepted, the Commission may engage
independent experts to assist in the review process. 
12 November 2020

Draft decision on our CPP Application from Regulator due

31 March 2021

Final decision on our CPP Application from regulator due

The Commission must make a final decision and set a CPP within 150 working days
after it has announced that the proposal is complete. During this time we will
work with the Commission to answer any questions it may have. A decision is
expected from the Commission by February 2021.   
01 April 2021

New pricing and reliability limits implemented based on final CPP Plan

Once approved, Aurora Energy’s customised price-quality path period would begin
on 1 April 2021, at the start of the regulatory year, and run until 31 March 2024.